Meeting Time: May 04, 2016 at 1:30pm PDT
The online Comment window has expired

Agenda Item

G.1) Discussion and consideration of the re-allocation of 2016 South Fork Road construction funding slated for 2016 to the design and construction of an asphalt surface on a one mile section of Last Chance Road and too add this section of Last Chance Road to the County maintenance program. The County planned to complete a road improvement project on the South Fork Road this year, but has run into permit delays. This would allow the County to do a road project this year due to limited project design requirements . This action if approved will move up the scheduled road work on Last Chance Road and remove the Last Chance Road Project from the Infrastructure Sales Tax list of projects. The South Fork Road Project will be moved to 2017.